Railroad Crossings Construction

Posted On: May 16, 2018

In early June, Union Pacific Railroad will be replacing the railroad crossings on Santa Fe Springs Road, Greenleaf, Gunn, Scott, and First Avenue. They’re replacing the asphalt with concrete panels for a smoother ride and longevity of the pavement. Each street will be closed for one day; they’re doing Scott Avenue on Saturday since it’s our busiest weekday location of these five streets.
 

Crossing Location Date of Construction Day of the Week 
Greenleaf Avenue 5/31/2018 Thursday
Santa Fe Springs 6/4/2018 Monday
Gunn Avenue 6/7/2018 Thursday
Scott Avenue 6/9/2018 Saturday
First Avenue 6/14/2018 Thursday